The installation processing for flat die small feed pellet mill.
Author:RICHi Time:2016-05-10
The installation processing for flat die small feed pellet mill.
First step
pipe (Picture 1) contact with the crusher cover (picture2) by bolts with seal materials ;
crusher cover (picture2) contact with crusher (picture3) by bolts with seal materials
if need to replace the sieve plate and hammer beater ,the same way to open that.
Then give power to this machine to test running
(please be carefully , all the parts assembled well);
Then make granular materials pile such as corn at the end of the pipe (picture1) . because There is a suction device inside of crusher to convey the materials into the crusher; then after grinding , the powdery materials will coming out to mixer.
The second step
Contact with the crusher outlet (picture 4 ) with the vertical mixer (picture 5-(1)) by bolts with seal materials
The picture 5-(2) ; you can dump powdery materials that there is no need to crush before pellet machine
The picture 5-(3) ;it is the outlet of the vertical mixer , there is a manual control there when you want to dumping the materials ,you can open that gate and control the flow feeding
Then give power to this machine to test running.
The third step
Put the screw feeder hopper under the mixer outlet and fix the screw feeder making a support for that ,then the outlet of the screw feeder should be upside of the pellet mill hopper
Give power to mixer to test the running.
The fourth step
The pellet mill , please check the details form the manual , then you can understand the design
The machine we have checked in our workshop , you just give power to this machine ,machine will running ,please check the control panel of that , you need a electrician to do the attached work;
Fix the pellet machine one the ground , by bolts or weld
Give the power to test machine running ;just press the buttons on the control panel.
Because of the machine is 400-600kg per hour ,and manual batching , so we suggest you to put 250kg materials by one time according to your formular ,then per hour 2 times dumping and mixing ; only when you finish one batch crushing and mixing ,then you can start next batch ,please check this information.